Skip to main content

Construction Updates

Subscribe to Rebuild Ryan Field newsletterView previous newsletters

Updates

Sept. 5, 2024 newsletter update

Aerial view of Ryan Field

View the full newsletter here.

Construction crews have been busy at the new Ryan Field, continuing work to lower the gradient to the future field height, reinforce the surrounding area and pour concrete foundations.

Mass excavation will near completion in the coming month, resulting in fewer trucks and less dust around the job site. Installation of earth retention system sheeting anchors also continues, wrapping up in early October.

Installation of underground utilities is set to begin in September, and concrete foundations will continue to be poured throughout the footprint of the future building.

Aug. 29, 2024

Aerial view of Ryan Field

Installation of earth retention anchors continues along the west side of the stadium, moving south, while mass excavation continues along the east side. Crews also continue to pour concrete foundations along the north end and are beginning to pour foundations along the east side.

 

Aug. 22, 2024

Installation of earth retention system lower soil anchors continues, along with mass excavation. Pouring of concrete foundations also continues along the south and north ends of the new stadium.

Aug. 16, 2024

Aerial view of Ryan Field

 Mass excavation continues this week, as crews place earth retention lower soil anchor along the south side and lower bracing along the east side. Pouring of concrete foundations also continues along the south and north ends. Additionally, the team continues to distribute 4-inch purple dot stickers to truck drivers to display in the upper left-hand corner of the windshield.

 

Aug. 8, 2024 newsletter update

Aerial view of Ryan FieldView the full newsletter here.

Several key activities will take place during the month of August. Deep foundations and the earth retention soil anchor drilling is scheduled to be completed this month. Underground utilities installation is set to begin, while the concrete foundation installation will continue into September. Mass excavation work also will continue into September, along with earth retention system bracing and testing.  

 

Previous Updates